# Case: the deliverable list that doesn't fit

> Twenty-five deliverables with effort ranges, 150 person-days of capacity. Add up effort by priority, challenge two false musts, and write Leo the scope decision with a drop order.

- Course: [Project Management Without the Bureaucracy: Run One Project from Brief to Closure](https://productovi.com/courses/project-management-without-bureaucracy.md)
- Module: Scope: what is in and what is out
- Lesson 8/32, ~36 min
- Source: https://productovi.com/courses/project-management-without-bureaucracy/deliverable-list-case

## Twenty-five lines, one Friday

**Alex Tutor:** End of October. The owners have filled the deliverable list: 25 lines, each with an owner, three effort values and a proposed priority. Leo wants the scope decision by Friday.

**Alex Tutor:** One more number, the plan's own assumption: the people booked for the project can give it **150 person-days** between 2 November and 29 January. That counts staff, the freelance authors and the illustrator.

**Dataset (CSV):** [Physics launch: deliverable list, October 2026](https://productovi.com/datasets/project-management-without-bureaucracy/deliverable-list-case/pm-deliverables.csv)

The owners' proposal. Effort in person-days of whoever does the work. budget_uah is cash from the 600,000 UAH ceiling (contractors, paid authoring, demo-lesson fees at 430 UAH, ads); staff time is not charged to it. Capacity before 29 January: 150 person-days (the plan's assumption).

- `id`: Deliverable id
- `area`: Branch of the breakdown tree
- `deliverable`: What is handed over
- `owner`: The one person who answers for it
- `optimistic_days`: Effort if things go well, person-days
- `likely_days`: Most likely effort, person-days
- `pessimistic_days`: Effort if things go badly, person-days
- `proposed_priority`: Priority the owner proposed: must, should or could
- `budget_uah`: Cash from the launch ceiling, UAH
- `depends_on`: Deliverables needed first (for the schedule)

**Sofia:** First question: do the owners' musts alone fit into 150?

**Alex Tutor:** Add up the likely values of every line marked "must". Likely, not optimistic: we plan on what usually happens.

> **Exercise:** Add up the **likely** effort of every deliverable the owners marked **must**. How many person-days?

## Two musts that aren't

**Leo:** 159 against 150. So even the musts don't fit. Then it's the date after all?

**Alex Tutor:** Not yet. First check that every must passes the test: can we open on 1 February and reach the goal without it? Owners mark their favourite items "must" in good faith.

**Vira:** I can guess which one of mine you mean.

**Danylo:** And which one of mine.

> **Exercise:** Which deliverables marked **must** fail the must test (the launch opens on 1 February and reaches its goal without them)? Select all that apply.

## The real musts

**Alex Tutor:** Video solutions and the parent dashboard pass the launch without them: tutors explain hard tasks in class, and parents ask the tutor. Both become could, on the after-launch list.

**Sofia:** Then the musts drop by 28 days. Let me recount.

**Alex Tutor:** And look at the range too. The musts' optimistic and pessimistic sums show how wide the uncertainty is, but don't plan on either sum: all lines going well, or all going badly, at once is unlikely.

**Alex Tutor:** How to handle that spread properly, with one shared buffer, is the next module but one.

> **Exercise:** Without D11 and D22, what is the **likely** effort of the remaining musts? In person-days.

**Alex Tutor:** The range is wide. Which number goes into the plan?

> **Exercise:** Across the effort range, the 17 real musts run from 94 person-days (every line optimistic) to 193 (every line pessimistic); the likely sum is 131. Which number should the plan use?

## Shoulds, money and the drop order

**Sofia:** Musts 131, so 19 days left. All five shoulds take 26, which is 7 over. Some shoulds have to go.

**Hanna:** And the money? Musts and all shoulds come to 503,450 UAH. That's under my 600,000.

**Alex Tutor:** So days bind, not money. Pick the shoulds by the days they cost and the value they bring to the goal, then keep a few days of room.

**Vira:** The mock exam is mine, and it's six days. I'd rather keep tutors explaining than lose a week of my time.

**Danylo:** The waiting list is two days and tells us in December if anyone wants physics. Keep it.

> **Exercise:** **True or false:** because must + should costs 503,450 UAH, under the 600,000 ceiling, the full must + should list can stay.

**Alex Tutor:** Now choose the shoulds and count the room.

> **Exercise:** Keep the 17 musts (131 likely person-days) plus three shoulds: D20 waiting list (2 days), D17 level report (5) and D24 January ads (5). How many person-days of room are left out of the 150?

**Sofia:** Musts, plus waiting list, level report and January ads: 143 days, 7 days of room. Diagrams and mock exam dropped first.

**Alex Tutor:** A defensible cut. Now the order for January: which of the kept shoulds goes first if something slips?

**Vira:** One more thing. 73 of the 131 must-days sit with me and my authors.

**Alex Tutor:** Note it for the schedule. Totals fit; whether one person's work fits in time is the question for November.

**Alex Tutor:** Vira's note raises a question. Check it before the drop order.

> **Exercise:** **True or false:** the kept list (143 person-days) fits into the 150 of capacity, so the work will be done by 29 January.

> **Exercise:** The kept list is the 17 musts plus D20 waiting list, D17 level report and D24 January ads (143 days). Write the **drop order** for January: the kept shoulds in the order they would go if something slips, each with one reason.

**Leo:** Send me one page: what's in, what's out, why, and what goes first if January goes wrong. I'll sign the order.

**Alex Tutor:** Write it so Leo can sign it without a meeting: numbers from the list, the must test for each disputed item, the margin, and the signed drop order.

**Sofia:** Then the page has five parts: the numbers, the false musts, in and out, the drop order, and Vira's load as the open question.

**Hanna:** Put the money line in too, even if it's good news. I want to see the 600,000 checked, not assumed.

**Alex Tutor:** And remember who signs: Leo, as the project sponsor, decides on scope. Your job is to make the choice clear, with numbers.

> **Exercise:** Write Leo the one-page scope decision for the physics launch.

> **Key ideas**
>
> - Add up effort by priority with the likely values and compare with capacity: here the owners' musts came to 159 person-days against 150.
> - Test every must before touching the date: two items (28 days) failed the test and became could.
> - The real musts are 131 likely days (94 to 193 across the range); plan on likely values and handle the spread with one buffer later.
> - Check which limit binds: must + should costs 503,450 UAH, under the 600,000 ceiling, but is 7 days over capacity.
> - Keep musts plus the most useful shoulds with room to spare (143 days, 7 days of room), and get a drop order signed.

**Alex Tutor:** Scope is settled. Next module: time. The list says what; the schedule says when, and whether 1 February really holds.

- Previous lesson: [Must, should, could: cut scope, not the date](https://productovi.com/courses/project-management-without-bureaucracy/must-should-could.md)