# Case: the contractor slips two weeks

> Three weeks before opening, the checkout contractor needs two more weeks. Re-plan from today, compare cutting scope, adding a developer and moving the opening, and write the decision note to Leo.

- Course: [Project Management Without the Bureaucracy: Run One Project from Brief to Closure](https://productovi.com/courses/project-management-without-bureaucracy.md)
- Module: Running the work: changes and re-planning
- Lesson 28/32, ~37 min
- Source: https://productovi.com/courses/project-management-without-bureaucracy/contractor-slips-case

## Monday, 11 January

**Alex Tutor:** Monday, 11 January, three weeks to opening. Remember R35 in the register, "the contractor may deliver late"? The trigger fired: there was no working checkout on the test site on 4 January.

**Danylo:** And this morning he wrote: he was due on Friday the 8th and needs ten more working days. Release on 22 January.

**Leo:** The date doesn't move. Exam season. Tell me what we do.

**Alex Tutor:** First the facts, then the options. Here's the contractor's task list with his new estimates, and what happens after his release.

> **The checkout chain**
>
> - The contractor is one developer and works through his tasks one after another.
> - After his release, the payment provider reviews the new product line: **5 working days**.
> - Then Danylo runs an end-to-end test with real test purchases: **2 working days**.
> - Classes open on Monday 1 February, so the chain must be ready by **Friday 29 January**: 15 working days from today, today included.
> - The original plan: release on 8 January, ready on 19 January, **8 working days** of buffer.
> - Budget left under the 600,000 UAH ceiling: **52,000 UAH**.
> - The contractor's offer: a second developer at 6,000 UAH a day, minimum 8 days; he needs 3 days to learn the code; with two, the release moves to 20 January.

**Dataset (CSV):** [Checkout chain: tasks left on 11 January 2027](https://productovi.com/datasets/project-management-without-bureaucracy/contractor-slips-case/contractor-remaining-tasks.csv)

The contractor's tasks with his new estimates, plus the provider's review and Danylo's test. Days are working days.

- `task_id`: Task id
- `task`: What the task delivers
- `priority`: must, should or could for the opening
- `owner`: Who does it: contractor, provider or danylo
- `planned_days`: The original estimate for the whole task
- `done_pct`: Progress to date, as the contractor reports it
- `remaining_days`: The new estimate of the days left
- `depends_on`: Tasks that must finish first

**Sofia:** Ten contractor days, then five for the provider, then two for testing. Against fifteen.

> **Exercise:** If the contractor ships **everything** in one release, how many working days does the whole chain need from today (his remaining work, the provider's review and the test)?

**Alex Tutor:** Before options: how much of his planned work is really earned?

> **Exercise:** Earned progress counts each contractor task as its **planned days × its done %**. Of his **25 planned days** (C1–C6), what percentage is earned so far?

## Two developers, half the time?

**Danylo:** Easy fix: take his second developer. Ten days of work, two people, five days. Release on the 15th.

**Alex Tutor:** That's effort divided by people, and it rarely holds. The new developer needs three days to learn the code, and the checkout can't be split between two people.

**Hanna:** The contractor's own estimate with two developers is 20 January, not the 15th. For 48,000 UAH. That leaves me 4,000.

**Sofia:** Release on the 20th, provider to the 27th, test to the 29th. On time, with zero buffer and an empty reserve.

> **Exercise:** Why does a second developer move the release only from 22 to 20 January, not to the 15th?

## Cut to the musts

**Alex Tutor:** Now look at the priority column. Which of his remaining tasks does the opening actually need?

**Sofia:** C3 checkout and C4 receipts are musts: six days. C5 calendar sync is a should, C6 instalments a could.

**Danylo:** If he ships the musts first, the provider can start on the 19th. He finishes C5 and C6 while they review, and we release those after opening.

**Vira:** Without calendar sync, Roman books tutors' evening slots by hand for two weeks. Annoying, not fatal.

> **Exercise:** The contractor ships only the **must** tasks first (C3 and C4) and the rest after opening. How many working days of buffer are left before Friday 29 January?

## Sixty percent done

**Danylo:** One thing hurts. Instalments are 60% done: three of five days, already paid. Two more days and families can pay in two parts from day one.

**Alex Tutor:** Those three days are spent under every option. Ask only: are two more days now worth the whole buffer?

**Sofia:** With C6 in the first release: release on the 20th, ready on the 29th, zero buffer. And the provider's review, R01 in the register, could still fail.

**Vira:** Families have paid for packages in one go for years. Instalments in February are a nice extra, not a reason to open late.

> **Exercise:** If the contractor ships only the musts first, the checkout chain is ready on 27 January with 2 working days of buffer before a provider review that may still fail. The instalments feature (C6, a could item) is 60 % done: three of its five days are already paid, and two days are left. Should it go into the first release?

## Who decides what

**Leo:** And the third option? Open on 15 February with everything in it.

**Alex Tutor:** That gives 8 days of buffer and costs two weeks of the exam season for every family, and the 120-learner check on 28 February gets two weeks instead of four. It moves a limit, so it's yours to decide.

**Alex Tutor:** Is the later opening simply the safe choice?

> **Exercise:** Leo, the sponsor, mentions a third option: open on 15 February with full scope, which gives 8 working days of buffer instead of a tight chain. **True or false:** opening on 15 February with full scope is the safest option, so the lead should choose it.

**Sofia:** Under our change rule, who decides each of these?

**Alex Tutor:** Check each against the threshold: up to two days of buffer and 10,000 UAH for the lead; the date, the ceiling, the out list and the success criteria for Leo.

> **Exercise:** Under the physics change rule, the project lead decides changes up to two days of buffer and 10,000 UAH from the reserve; Leo, the sponsor, decides in writing on the date, the budget ceiling, the out list, the success criteria and anything above the threshold. Match each decision to who makes it.

**Alex Tutor:** Vira's question first: what if the review fails anyway?

> **Exercise:** You recommend option A (musts first, ready 27 January, 2 days of buffer). Which trigger and fallback belong in the note?

## The note to Leo

**Leo:** Put it on one page today. I'll decide by Wednesday.

**Hanna:** Every option with its cost in UAH, please, including the one that costs nothing.

**Vira:** And say what we do if the provider's review fails anyway. Two days of buffer isn't much.

**Sofia:** Forecast from today, three options, my recommendation, a trigger and a fallback, the decision I need.

> **Exercise:** Write the decision note to Leo about the contractor's two-week slip.

> **Key points**
>
> - Re-plan from today: 10 + 5 + 2 = 17 working days needed against 15 left. The plan's 8-day buffer is gone.
> - Two developers don't halve the time: onboarding and an unsplittable task move the release only from 22 to 20 January, for 48,000 UAH.
> - With a fixed date, scope flexes: musts first gives 2 days of buffer at no cost.
> - Work already paid (instalments 60% done) is the same under every option; it doesn't decide.
> - The lead decides inside the threshold; spending the reserve or moving the opening is the sponsor's call, in writing, logged.

**Alex Tutor:** That closes the running stage. Next: getting the result accepted, handing it over, and checking whether families really came.

- Previous lesson: [Re-plan from today](https://productovi.com/courses/project-management-without-bureaucracy/re-plan-from-today.md)
- Next lesson: [Build, buy or hire: contracts by how clear the scope is](https://productovi.com/courses/project-management-without-bureaucracy/build-buy-or-hire.md)

---
Productovi Learning. Free, no sign-up needed to read.