# Build, buy or hire: contracts by how clear the scope is

> Decide per piece of work, pick a fixed price or time and materials by how clear the scope is, write a short request for proposals and pay for accepted work.

- Course: [Project Management Without the Bureaucracy: Run One Project from Brief to Closure](https://productovi.com/courses/project-management-without-bureaucracy.md)
- Module: Closing and learning
- Lesson 29/32, ~24 min
- Source: https://productovi.com/courses/project-management-without-bureaucracy/build-buy-or-hire

## Where we are

**Alex Tutor:** Late January 2027 at Klasna: the physics launch you lead for Leo opens on its fixed date, Monday 1 February. This last stage closes the project: settle contracts, hand over to operations, check the results in March and record what the next project should learn.

**Vira:** The illustrator sent the last batch of practice-set diagrams. I want 40 more for the April mock exams. Same person, or do we ask around?

**Danylo:** Before you answer: we built the diagnostic test, we buy the video rooms, we hired out the diagrams. Three choices, none an accident.

**Alex Tutor:** That's **build, buy or hire**, decided per piece of work. Build what is core and will keep changing. Buy what already exists. Hire for clear, bounded pieces your team can't do well.

**Sofia:** So the test was build because Danylo's team will keep tuning it after launch?

**Alex Tutor:** Exactly. Who maintains it after launch often decides. Diagrams don't change every week; the test will.

> **Exercise:** Match each piece of the physics launch to the choice that fits it best.

## The contract follows the scope

**Sofia:** How did we pay the illustrator?

**Alex Tutor:** A **fixed price**: 120 diagrams at 450 UAH, 54,000 UAH in total, in three batches of 40. It worked because the scope was clear up front: the problems, the style, the file format.

**Vira:** My checks were in the contract: each diagram matches its problem, Ukrainian labels, an editable vector file. Batch two had six wrong arrows; we paid once they were fixed.

**Alex Tutor:** That's the second habit: **pay for accepted deliverables**, not hours or promises. Acceptance criteria make "done" checkable by both sides.

**Danylo:** The platform contractor was the opposite. In November nobody knew how big booking by subject really was.

**Alex Tutor:** With an unclear scope, a fixed price makes the contractor pad the price or fight every change. A **time-and-materials** contract pays hours at an agreed rate. The risk of growth is yours, so add a cap and a weekly check of what was delivered.

> **Exercise:** **True or false:** a fixed price is always safer for Klasna, because the contractor carries the risk of extra effort.

**Alex Tutor:** Apply that to the platform contractor's work in November.

> **Exercise:** In November nobody knew how big "booking by subject" really was, and Klasna hired the platform contractor for it. Which terms fit that work best?

## A short request for proposals

**Vira:** So for the 40 new diagrams: fixed price again?

**Alex Tutor:** Yes, the scope is as clear as before. But don't re-hire by habit: send three illustrators a short request for proposals. What you need, by when, how you'll accept, how you'll choose.

**Sofia:** How will we choose?

**Alex Tutor:** Weighted criteria, each with its direction written down. Say quality 40%, price 30%, date 20%, revisions included 10%. Price: 5 is the lowest. Date: 5 is the earliest.

**Danylo:** Why spell out the direction? Cheaper is obviously better.

**Alex Tutor:** Obvious, until someone scores price by size and the dearest bid wins. Written down, two people score a bid the same way. And a hard requirement is a gate, not a weight: a sample with wrong physics is out, however cheap.

> **Exercise:** Three bids for the 40 diagrams, scored 1–5 (5 = best in the stated direction). Weights: quality 40%, price 30% (5 = lowest), date 20% (5 = earliest), revisions 10%. Gate: quality at least 4.
>
> - **A:** quality 5, price 2, date 3, revisions 4
> - **B:** quality 3, price 5, date 5, revisions 2
> - **C:** quality 4, price 4, date 3, revisions 3
>
> Which bid wins?

**Alex Tutor:** And where does correct physics go: a weight or a gate?

> **Exercise:** **True or false:** "the physics in every diagram is correct" should get the biggest weight in the scoring, say 50%.

## Pay for what you accept

**Sofia:** And if the new illustrator asks for half the money up front?

**Alex Tutor:** A small advance can be fair for a freelancer. Tie the rest to accepted batches: 40 diagrams in two batches of 20, each paid after Vira's check.

**Hanna:** From my side: write down who signs the acceptance and where. I pay against a signed batch, not a chat message saying "looks fine".

**Alex Tutor:** So what do you agree with the new illustrator?

> **Exercise:** The new illustrator asks for half of the 40-diagram fee up front. Vira, who owns the physics curriculum, checks every diagram, and Hanna, head of finance, pays only against a signed acceptance. What do you agree?

**Alex Tutor:** One more thing: from Monday physics is operations, so Vira owns this order and pays from the operating budget, not the project's 600,000. Your job is to leave the request template behind.

**Vira:** So the project hands me a template, not another task. I like that.

> **Exercise:** Put the steps of hiring the illustrator for the 40 diagrams in order.

## What goes into the request

**Sofia:** Let me list what the request needs before I write it.

**Alex Tutor:** Good: scope, deadline, acceptance, contract and payment, weights with directions, the gate. Nothing that reveals what other bidders offered.

**Danylo:** And a date for the decision, so nobody waits for an answer forever.

**Alex Tutor:** Yes. And ask for a two-diagram sample: the cheapest quality check before signing.

> **Exercise:** What belongs in the request for proposals for the 40 diagrams? Choose all that apply.

## Your turn: the request for 40 diagrams

**Vira:** The April mocks start on 5 April. I need the diagrams by 20 March to check them.

**Alex Tutor:** Then write the request Vira can send this week, short enough to read in two minutes.

**Sofia:** Scope, date, checks, fixed price per accepted batch, weights with directions, one gate.

**Hanna:** And the name of whoever signs the acceptance, please.

> **Exercise:** Write the **short request for proposals** for 40 diagrams for the April mock exams (5–8 lines): scope, deadline, acceptance criteria, contract type and payment, 3–4 weighted criteria with the direction of each, one gate, who signs the acceptance. The April mock exams start on 5 April, and Vira needs the diagrams by 20 March to check them.

> **Key points**
>
> - **Build, buy or hire** is decided per piece of work: build what is core and will keep changing, buy what exists ready, hire for clear, bounded pieces.
> - Ask who will maintain it after launch.
> - **Fixed price** when the scope and acceptance criteria are clear; **time and materials** when they aren't, with a cap and a weekly check.
> - A short request for proposals: scope, deadline, acceptance, contract and payment, weighted criteria with the direction of each, a hard requirement as a gate, a decision date.
> - Pay for accepted deliverables, signed by a named person.
> - After opening, new orders are operations; the project leaves a template.

**Alex Tutor:** Next: the handover itself. From Monday someone other than the project team runs physics. Who, and with what?

- Previous lesson: [Case: the contractor slips two weeks](https://productovi.com/courses/project-management-without-bureaucracy/contractor-slips-case.md)
- Next lesson: [Acceptance and handover to operations](https://productovi.com/courses/project-management-without-bureaucracy/acceptance-and-handover.md)

---
Productovi Learning. Free, no sign-up needed to read.