# Acceptance criteria: what "done" means

> "Good lessons" is a wish nobody can accept. Write checks a named person can run, agree them before the work starts, and say what happens when one fails.

- Course: [Project Management Without the Bureaucracy: Run One Project from Brief to Closure](https://productovi.com/courses/project-management-without-bureaucracy.md)
- Module: Scope: what is in and what is out
- Lesson 6/32, ~23 min
- Source: https://productovi.com/courses/project-management-without-bureaucracy/acceptance-criteria

## Done according to whom?

**Alex Tutor:** The deliverable list is up, with owners and effort ranges. Each line still needs one thing: what "done" means, and who says so.

**Leo:** For the curriculum, write "good lessons". We all know what good means.

**Vira:** I know what I mean by good. The freelance authors don't, and neither will the person who checks their work in December.

**Alex Tutor:** That's the deliverable nobody can accept. "Good lessons" is a wish: the authors can't aim at it, and nobody can say no to it without a fight.

**Alex Tutor:** **Acceptance criteria** are checkable conditions, agreed before the work starts, that one deliverable must meet. And a named person runs the check.

**Sofia:** Named by whom? The author knows the work best.

**Alex Tutor:** Not the author. The person who will rely on it, or the expert who can judge it. For the curriculum and practice sets, that's Vira.

> **Exercise:** Which line is an **acceptance criterion** for the mechanics unit, not a wish?

**Alex Tutor:** Criteria need a name next to them. Whose?

> **Exercise:** Danylo builds the physics landing page. Who is the best person to accept it?

## Turn each word into a check

**Vira:** A good practice set is correct, at exam level and has answers. That's what I need.

**Alex Tutor:** Then turn each word into a check. Take "correct": how would you check three hundred tasks?

**Vira:** I can't solve them all. I can solve a random sample myself and compare with the authors' answers.

**Alex Tutor:** Write exactly that: a set is accepted when Vira solves a random sample of 20 tasks and finds no factual errors, and every task has an answer and an exam topic.

**Danylo:** And if she finds one error in twenty?

**Alex Tutor:** Then one error is a sign of more. The set goes back, the author rechecks all of it, and Vira takes a new sample. Agree that now, too.

> **Exercise:** Which conditions for accepting a practice set can Vira actually **check**? Select all that apply.

**Alex Tutor:** Put Vira's steps in order, from the word to the rule.

> **Exercise:** Put the steps in order to turn Vira's word “correct” into an acceptance criterion.

## A test that places learners

**Danylo:** My diagnostic test then. Criterion: "works and is accurate".

**Alex Tutor:** "Works" needs devices and a result you can see. "Accurate" needs something to compare with. Who knows a learner's real level?

**Vira:** I do, after a twenty-minute talk with the learner.

**Alex Tutor:** Then: the test places three pilot learners at the same level Vira finds on her own, it runs on a phone and a laptop, and every result is saved.

**Sofia:** Three learners is hardly proof.

**Alex Tutor:** It isn't, and it shouldn't pretend to be. It's a smoke check that catches a broken test before launch. Whether placement is right shows in the February data; write that limit down.

> **Exercise:** **True or false:** if the diagnostic test places all three pilot learners at the level Vira finds, that proves the test places learners accurately.

## Criteria and the definition of done

**Danylo:** My team already has a checklist for everything we ship: code reviewed, tested, released. Isn't that the same?

**Alex Tutor:** That's a **definition of done**: one checklist for every piece of work. Acceptance criteria belong to one deliverable: what this landing page must do for families.

**Sofia:** Then for the landing page: it shows the 8, 16 and 32-lesson packages with prices, it books a physics lesson end to end, and it works on a phone. I accept it.

**Alex Tutor:** Good, and you're a fair acceptor because you didn't build it. Add how you'll check: a test purchase on a phone.

> **Exercise:** Match each line with what it is.

## Agree before, decide when it fails

**Alex Tutor:** When to agree criteria? Before the work starts. Criteria written after delivery tend to describe whatever was delivered.

**Vira:** The authors may say a sample of 20 is too strict.

**Alex Tutor:** Then let them argue now. Criteria agreed in October are a shared target; in January they are a fight.

**Alex Tutor:** Timing matters as much as wording. Check it.

> **Exercise:** **True or false:** it's safer to write acceptance criteria after a deliverable arrives, when you can see what it actually looks like.

**Vira:** Let's try it on a bad day: practice set 2 arrives late, and my sample finds two errors.

**Danylo:** Three days before launch, everyone will want to just fix those two.

> **Exercise:** Three days before launch, Vira's sample of 20 tasks from practice set 2 finds two factual errors. What do you do?

**Leo:** And if something fails a criterion a week before launch?

**Alex Tutor:** Then you decide with the criterion in front of you: fix it, cut it, or accept it with a written exception Leo signs. What you don't do is quietly lower the bar.

**Alex Tutor:** Now write criteria for one more deliverable: Roman's tutor onboarding.

> **Exercise:** Write acceptance criteria for **tutor onboarding** (Roman's deliverable): two or three conditions someone can check, how each is checked, and who accepts.

**Sofia:** So every line of the list gets two or three checks and one name.

**Alex Tutor:** And a way to check: a sample, a test purchase, a pilot. A check without a way to run it is still a wish.

> **Key ideas**
>
> - "Good lessons" is a wish. **Acceptance criteria** are checkable conditions for one deliverable, agreed before the work starts.
> - A named person accepts: the expert or the user, not the author or builder.
> - Turn each vague word into a check with a method: a sample of 20 tasks with no factual errors, three pilot learners placed as Vira places them, a test purchase on a phone.
> - A small check is a smoke test, not proof; write its limit down.
> - The **definition of done** applies to all work; acceptance criteria to one deliverable.
> - When a criterion fails: fix, cut, or a signed exception. Never a quietly lowered bar.

**Alex Tutor:** Next: the list is longer than the time. We sort it into must, should and could, and cut scope instead of the date.

- Previous lesson: [Break the work down from deliverables](https://productovi.com/courses/project-management-without-bureaucracy/break-the-work-down.md)
- Next lesson: [Must, should, could: cut scope, not the date](https://productovi.com/courses/project-management-without-bureaucracy/must-should-could.md)

---
Productovi Learning. Free, no sign-up needed to read.